INSTALLATION TIMELINE

Z

1. SITE ASSESSMENT (2-5 BUSINESS DAYS)

Site assessor measures and takes readings of the roof. Access to electrical panel and interior is needed.

2. ENGINEERING AND DESIGN (3-5 WEEKS)

Our engineering team designs and plans your solar project to ensure the best system possible.

3. PERMITS (NYC: 8-10 WEEKS | UPSTATE/LONG ISLAND: 3-5 WEEKS)

We apply for permits and communicate with your utility company.

4. INSTALL (2-3 BUSINESS DAYS)

Our installation team installs and hard-wires your solar system.

U

5. INSPECTION (3-8 WEEKS)

Your city’s building department conducts inspections to ensure the quality and safety of the installation.

6. SYSTEM ACTIVATION (2-4 WEEKS)

Once we receive approval from your utility, it is safe to activate your system. All systems are GO! Enjoy solar with SunPower® by Kamtech Solar.